Challenge
At our client’s facility, bottles needed to be transferred from the blow molding machine to the filling line. However, the factory floor was fully occupied, making it nearly impossible to install conventional conveyors.
Solution
A vibrating shaker unit ensured a steady product flow, and bottles were elevated to a conveyor line suspended 5 meters above the floor. The automation system optimized flow by transferring only the required number of bottles based on real-time data from the filling machine.
Result
The line reached a capacity of 16,000 bottles per hour. Space constraints were resolved, and the production flow became more efficient and uninterrupted.